 |
|
HOME > TRIPS > Gonaives, Haiti 2009
Gonaives, Haiti 2009
 |
 |
HAITI 2009 IN DETAIL ... Fellowship members began planning for the Jan. 31 to Feb. 14, 2009, trip to Gonaives in March 2008. The CMF Board presented an overview of the Gonaives trip to Fellowship members, who approved the proposal by majority vote.
A total of 18 members will be traveling to Haiti. Each member assumes the responsibility of paying the cost of his or her airline travel, transportation in country, and food, which allows all funds raised by the group to be designated for project work.
PROJECT Building on the work of previous missionary groups, CMF members will be adding a 42'x106' roof to the church in two phases. The first phase will be comprised of fabricating steel trusses, and the second phase installing the trusses, sheeting and finishing the roof.
FUNDING As explained in the Project Notes at left, the original estimate for completing the roof was $20,000; however, after two, separate hurricanes devastated the region, the project cost increased by approximately 27 percent to $27,000.
CURRENT FUNDING LEVEL ... As of Jan. 20, 2008, the group has raised approximately $30,000 toward the project. |
|
 |
| |
PROJECT: 4,000-SQUARE-FEET ROOF
GONAIVES, HAITI / Jan. 31, 2009 to Feb. 14, 2009
A team of 18 men and women added a 4,000-square-feet roof to a church, pictured right, extensively damaged by the hurricanes that devastated Gonaives and the surrounding area in September 2008. The group, with the exception of its leaders, was split into two teams: The first team departed for Haiti in Jan. 31 and was replaced Feb. 7 when the second team arrived. The missionaries completed the roof with ample time remaining to tour the countryside, revisit former project sites, and identify potential projects. E-mail updates sent while in country were used to create the Gonaives 2009 Project Diary. | |  |
| | | |  |  | Upon arriving in Gonaives, the missionaries were greeted by a sign made by church members. The team stayed in the church's guest house, which is used exclusively by visiting missionary teams. |
| | | |  |  | The effort to build a 106-feet by 42-feet roof was divided into two parts: The first part required the team to construct the trusses that would be support the church roof. Because of space limitations, the trusses were built in two parts. A total of 44, 22-feet trusses and purloins were built and installed in six days. |
| | | | 
|  | One of the biggest challenges before the group was how to raise the trusses after they had been constructed; at its peak, each truss was 27 feet from the ground. Ultimately, the team raised the truss halves and stationed a welder on makeshift scaffolding to fuse the halves together and add the purloins. The scaffolding was erected on top of the existing roof. |
| | | |  |  | In order to secure the east end of the roof, the team erected a second set of scaffolding in the area that will become the youth room, which is adjacent to the sanctuary. |
| | | |  |  | Missionaries Terry Parker, Dennis Forsythe, and Mark St. Clair squared the end of the purloins to ensure the roof was started correctly. Once completed, five team members lined one half of the the roof to work as efficiently and expediently as possible. |
| | | |  |  | Incredibly, after nine days of work, the new roof was completed. In the next few months, the old roof will be removed, which will balconies to be built, creating additional seating for the 400-plus member congregation.
For more pictures, please take a moment to view the completed project pictoral (click here). |
| | | |
|
|
|
CHRISTIAN MISSIONARY FELLOWSHIP 1414 Porstsmouth Rd, Peebles, Ohio 45660 TEL:(937) 587-5376
| COPYRIGHT 2009-2011. ALL RIGHTS RESERVED |
|
|